RFQ - Central Office Renovations Addendum 2
To request a copy of the RFQ - Central Office Renovations, please click here.
To request a copy of the RFQ - Central Office Renovations Plans and Pricing, please click here.
Submission deadline - 2:00 p.m., January 14, 2021
- Addendum 1 - published January 12, 2021
ADDENDUM #1
Addendum #1 does not add additional time to the bid date -
Bids are due January 14, 2021 @ 2PM
- The entire project is on job/contract but needs to be priced in 3 Phases with total HVAC and Plumbing separate (please see new Bid Form)
- The entire project will be completed all at the same time, not divided into phases.
- All items (furniture, cubicles, filing cabinets) the responsibility of the contractor to dispose/salvage
- ACM/LBP tests have been performed with no positive traces. This test has expired so a new test is currently being performed. Mediation if needed, will be discussed in an addendum
- All flooring including the ceramic tiles on lower level and new LVP in upper level phase III will be removed
- Stair treads will be replace per plans/specifications
- No bid bond is currently required. Payment and performance bond will be discussed with awardee
- The entire roof has been replaced; no roof work/repairs are included in this contract
- The Piggy back clause is for another Housing Authority to use the awardee for one of their projects without having to go out for bid.
- The elevator is to small to move drywall upstairs
- Access Control will be installed by Irmo Lock and Key - They will require conduit and power
- HVAC Controls will need to be coordinated with Johnson Control
- New rubber treads on one of the sets of stairs - See attached drawings "Stair Treads"
- Cove Base - See attached drawing "Cove base"
- Electrical/Lighting: Answers will be forth coming in Addendum #2
- Addendum 2 - published January 12, 2021
ADDENDUM #2
Addendum #1 does not add additional time to the bid date - Bids are due January 14, 2021 @ 2PM
There have been questions regarding the electrical drawings:
Electrical
- Clarify location of any Type CEX and/or Type EM Light Fixtures (none shown on E101 or E102).
- Verify that no Light Fixtures are needed in Work Room 213 (none shown on E102).
- Clarify Type C Light Fixture-The lighting schedule calls for a 2x2 drop in fixture (as indicated on E101) but E102 indicates a 2x4 drop in fixture.
- Verify the same Type Light Fixture is to be installed in Room 200 (2nd floor lobby) and in the Board Room Lobby (open to floor below), as shown on E102.
Please bid per drawings.
Columbia Housing has numerous and ongoing business opportunities for providers of various services and products. We strive for a fair, efficient, and open business opportunity process. If you are a supplier of products, goods and/or services, Columbia Housing may have opportunities for you and your firm.