Marion Street

Marion Street Highrise

Serving Senior Residents of Columbia Housing since 1975.

Over the last 45 years, Marion Street has developed maintenance issues that make it more cost effective to move the current residents.  As a result, we are no longer filling empty units at Marion Street and will begin to move the remaining residents in Spring of this year.

Below is a timeline of action steps Columbia Housing has taken to date regarding Marion Street and a timeline regarding next steps for current residents of the community and disposition of the property.

We will continue to update our timeline as the process moves forward.


2021:

Marion Street On the Move newsletter

Door to door chats with the residents of Marion St. on January 27, 2021

  • January 14, 2021: Board Workshop - Marion Street Disposition Presentation
    2020:
  • August 24, 2020: Resident Executive Council Meeting (update on Marion Street Disposition)
  • August 17, 2020: Marion Street Meeting with Residents (Socially Distanced Door-to-Door)

Flyer for door to door visits with Marion St. residents on August 17, 2020

  • February 25, 2020: Resident Executive Council Meeting (update on Marion Street Disposition)
  • February 13, 2020: Received results of Comprehensive Needs Assessment
  • February 5, 2020: Marion Street Meeting with Residents
  • January 28, 2020: Resident Executive Council Meeting (update on Marion Street Disposition)
  • January 28, 2020: Resident Executive Council Meeting (update on Marion Street Disposition)
  • December/January 2020: Comprehensive Needs Assessment and unit inspections underway
  • November 2019: Comprehensive Needs Assessment task order issued to Environmental Consultant
    2019:
  • November 2019: Provided updated communications to HUD on the status of the vacant units and desired plans for securing an early relocation approval & Section 18 Disposition Approval
  • October 17, 2019: Board approved a pool for Environmental Consultants per Resolution 2019-663
  • October 10, 2019: Executive Committee Agenda - contract services for Phase I Environmental Consultants
  • September 24, 2019: Resident Executive Council Meeting (update on Marion Street Disposition)
  • September 2019: Issued solicitation for the procurement of Phase 1 Environmental Consultants
  • July/August 2019: Development Team analysis of property